Friday, June 29, 2007

Permit Ready to be issued

Got today the call that the permit is ready to be issued (after paying some additional $700 to the City). Only now need to have the general contractor lined up and his license information.

First major hurdle (the paper work) is done!

Thursday, June 21, 2007

Updated elevation drawings

Finally got this drawing updated by the architect. Went straight to City Hall to file the revision.

Tuesday, June 5, 2007

Vacation

Architect was supposed to update our the site plan so the permit application did not stall at the Planning Department, but he suddenly went on vacation. Back Next week. Bummer!

Tuesday, May 29, 2007

Letter from the city

Got a letter today from the city. Inconsistency in regards to the elevation curves. I should have seen that as well, but more importantly, it should never have left the architect in that shape.

Calling architect. He tells me he'll fix it quickly. Good.

Wednesday, May 16, 2007

Design finally done

The architect was finally done today (after getting the drawings PE stamped) and after a quick review, I went to the city to file for a permit.

Intake fee of some $300 paid and quick review by Darrel Harmon who also granted the application "fast track" status (meaning that the entire process can take as little as two-three weeks compared to normally over eigth weeks).

Now it is just "wait and see"...

As a side note, I always wonder how the ones who are attacking remodeling projects WITHOUT filing for permits manages to get away with it. In WA state these days, on "Form 17", you have to indicate whether you have done work that was not permitted and inspected, and if you answer "no", and a later owner finds out that you had work done w/o permiting it, it will come back to haunt you.