Got today the call that the permit is ready to be issued (after paying some additional $700 to the City). Only now need to have the general contractor lined up and his license information.
First major hurdle (the paper work) is done!
Friday, June 29, 2007
Thursday, June 21, 2007
Updated elevation drawings
Finally got this drawing updated by the architect. Went straight to City Hall to file the revision.
Tuesday, June 5, 2007
Vacation
Architect was supposed to update our the site plan so the permit application did not stall at the Planning Department, but he suddenly went on vacation. Back Next week. Bummer!